Report 57: 07.03.2006
Progress: New wheels and power switch.
Time: 7 hours
|
|
Report 56: 04.24.2006
Progress: Stripped down and plated.
Time: 15 hours
|
|
Report 55: 07.11.2005
Progress: Fixed uMOB2 height issues, rebuilt laptop battery pack, fabricated new Lexan top plates
Time: 22 hours
|
|
Report 54: 06.20.2005
Progress: Mounted uMOB2, new VIA box shock mounts (iteration 1 and 2), two new top panel members
Time: 11 hours
|
|
Report 53: 06.14.2005
Progress: Constructed static tensioner arms, repaired tracks
Time: 4 hours
|
|
Report 52: 05.24.2005
Progress: A lot of work on the PWM interface, not a lot of results
Time: 27 hours
|
|
Report 51: 05.19.2005
Progress: Built and tested the PWM coprocessor board
Time: 7 hours
|
|
Report 50: 05.16.2005
Progress: Shock mounted and wired the new speed controllers.
Time: 8 hours
|
|
Report 49: 05.10.2005
Progress: Stapled track, made new tensioner bars and speed controller mounts. Cut allowances in the top panel for the new controllers.
Time: 4 hours
|
|
Day 48: 04.07.2005
Progress: Finished final assembly.
Time: 8 hours
Status: I think we made it.
|
|
Day 47: 04.05.2005
Progress: Installed track and computer system.
Time: 8 hours
Status: We'll make it, provided the controller gets here Thursday morning
|
|
Day 46: 04.02.2005
Progress: Ground drive axles to fit, did some wiring.
Time: 5 hours
Status: Behind schedule, but I should be ready by Friday
|
|
Day 45: 03.31.2005
Progress: Rebuilt drive axles, modified tensioner arm, un-wired the smoked controller.
Time: 10 hours
Status: Behind schedule, ten days
|
|
Day 44: 03.26.2005
Progress: Fixed drive sprockets, major test, broke drive sprockets, many hours of diagnosis, discovered cooked speed controller.
Time: 19 hours
Status: Behind schedule, ten days
|
|
Day 43: 03.24.2005
Progress: Computer wiring, finished track seams, installed tracks, cooked the serial cable, figured out that we cooked the serial cable.
Time: 17 hours
Status: Behind schedule, ten days
|
|
Day 42: 03.22.2005
Progress: Sewed other track, glued. Finished heat exchanger. Designed a process for loading the track.
Time: 15 hours
Status: Behind schedule, ten days
|
|
Day 41: 03.20.2005
Progress: Bent all of the aluminum tubing for the heat exchanger, and manufactured most of the fittings. Cut Lexan panels for the top.
Time: 11 hours
Status: Behind schedule, ten days
|
|
Day 40: 03.19.2005
Progress: Sewed up one track. Shock mounted the VIA enclosure.
Time: 6 hours
Status: Behind schedule, ten days
|
|
Day 39: 03.17.2005
Progress: Glued track. Front axle done, tensioners done, battery mounts done.
Time: 9 hours
Status: Behind schedule, ten days
|
|
Day 38: 03.15.2005
Progress: Trimmed the paddles and glued the track. Built the tensioner arms.
Time: 7 hours
Status: Behind schedule, ten days
|
|
Day 37: 03.13.2005
Progress: Finished cutting the tracks. Cut half the paddles.
Time: 6 hours
Status: Behind schedule, nine days
|
|
Day 36: 03.10.2005
Progress: Lots of track work, but not done yet.
Time: 6 hours
Status: Behind schedule, eight days
|
|
Day 35: 03.09.2005
Progress: Tensioner arm pivot fitting drilling, VIA enclosure bolt hole drilling, gasket cut.
Time: 3 hours
Status: Behind schedule, seven days
|
|
Day 34: 03.08.2005
Progress: Two and a half of four track cuts.
Time: 3 hours
Status: Behind schedule, seven days
|
|
Day 33: 03.06.2005
Progress: Cleaned shop, finished spring mounts, started tensioner arms.
Time: 5 hours
Status: Behind schedule, seven days
|
|
Day 32: 03.05.2005
Progress: Finished drive axles.
Time: 6 hours
Status: Behind schedule, seven days
|
|
Day 31: 03.04.2005
Progress: Mostly manufactured nitrogen spring mounts. Fixed chop saw wiring.
Time: 2 hours
Status: Behind schedule, seven days
|
|
Day 30: 03.03.2005
Progress: None
Time: 6 hours
Status: Behind schedule, seven days
|
|
Day 29: 03.01.2005
Progress: Some cutting, some gluing. Finally got organized.
Time: 3 hours
Status: Behind schedule, five days
|
|
Day 28: 02.27.2005
Progress: Added final chassis member, mounted and wired 6V batteries, finished suspension, assembled, tested.
Time: 10 hours
Status: Behind schedule, four days
|
|
Day 27: 02.24.2005
Progress: Removed drive axles, manufactured and installed suspension and glides for two axles.
Time: 9 hours
Status: Behind schedule
|
|
Day 26: 02.23.2005
Progress: Finished all three ground axles
Time: 5 hours
Status: Behind schedule
|
|
Day 25: 02.22.2005
Progress: First major test -- successful. More VIA box gluing, cut and marked the track, burned chop-saw, checked electronics fit, sealed speed controller.
Time: 10 hours
Status: Still behind schedule
|
|
Day 24: 02.21.2005
Progress: Manufactured the axles and hard disk mounts. VIA box epoxy: round two.
Time: 7 hours
Status: Still technically behind schedule
|
|
Day 23: 02.20.2005
Progress: Cut all the plastic for the VIA enclosure, glued the bottom half.
Time: 5 hours
Status: Behind schedule
|
|
Day 22: 02.19.2005
Progress: Welded speed controller mounts and manufactured aft battery mount.
Time: 3 hours
Status: Behind schedule
|
|
Day 21: 02.17.2005
Progress: Wired major electrical system.
Time: 10 hours
Status: Behind schedule
|
|
Day 20: 02.15.2005
Progress: Finished major structure. Mounted motors and drive train. Cut and mounted roller chain.
Time: 7 hours
Status: One day behind schedule
|
|
Day 19: 02.13.2005
Progress: Fixed the motor fit problem (to the extent that I will be able to), made and installed five members.
Time: 3 hours
Status: Behind schedule
|
|
Day 18: 02.12.2005
Progress: Built motor mounts. Almost finished major structure in aft half of chassis.
Time: 9 hours
Status: Cautiously pessimistic
|
|
Day 17: 02.10.2005
Progress: Cut, shaped, and welded 13 members. Aligned drive axle supports, checked battery fit, discovered battery defect.
Time: 9 hours
Status: Outlook not so good
|
|
Day 16: 02.08.2005
Progress: Cut, drilled, shaped, brushed, aligned, and welded eight cross-members.
Time: 5 hours
Status: A little worried
|
|
Day 15: 02.06.2005
Progress: Ground welds, flipped over, welded, ground welds, welded back, welded supports, ground corners, drilled holes, bolted to side panels.
Time: 5 hours
Status: Still a little worried, but feeling a bit better
|
|
Day 14: 02.05.2005
Progress: Finished welding the back panel piece and welded the first side of the top panel.
Time: 3 hours
Status: A little worried
|
|
Day 13: 02.03.2005
Progress: Cut remaining members for top platform. Ground all 30 pieces to final fit.
Time: 6 hours
Status: A little worried
|
|
Day 12: 02.01.2005
Progress: Laminated template to table. Cut and brushed thirteen members.
Time: 2 hours
Status: On schedule
|
|
Day 11: 01.31.2005
Progress: Drew, cut, and folded all individual templates for top panel. Finished master template.
Time: 6 hours
Status: On schedule
|
|
Day 10: 01.30.2005
Progress: Ground welds, flipped over, welded, grounded, and brushed second side panel. Abuse tested. Patched up cracks and evaluated results.
Time: 4 hours
Status: On schedule
|
|
Day 9: 01.29.2005
Progress: Cleaned second side panel members, touched up fits, completed first side welding.
Time: 3 hours
Status: On schedule
|
|
Day 8: 01.27.2005
Progress: Finished first chassis side panel.
Time: 5 hours
Status: On schedule
|
|
Day 7: 01.25.2005
Progress: Welded roughly one third of one side panel.
Time: 2 hours
Status: On schedule
|
|
Day 6: 01.23.2005
Progress: Ground remaining pieces for both sides of the chassis. Drilled, welded, and tapped eight weld nuts for clamping. Aligned eight members for welding.
Time: 4 hours
Status: On schedule
|
|
Day 5: 01.22.2005
Progress: Ground 38 steel members to shape.
Time: 3 hours
Status: On schedule
|
|
Day 4: 01.20.2005
Progress: Welded eight weld nuts.
Time: 2 hours
Status: On schedule
|
|
Day 3: 01.19.2005
Progress: Drilled some holes. It took much longer than it should have. Reasonably happy with the result.
Time: 2 hours
Status: On schedule
|
|
Day 2: 01.18.2005
Progress: Cut all of the remaining steel for the chassis sides. Marked all pieces for final fitting.
Time: 4 hours
Status: On schedule
|
|
Day 1: 01.17.2005
Progress: Cut and cleaned most of the steel for one chassis structure plane. Marked pieces for final fitting.
Time: 5 hours
Status: On schedule
|